News

KONYA CIPS DCVG SERVICE

We have completed the 25 km CIP Survey (Checking and interpreting the cathodic protection performance at every 1 meter of the pipeline.) and DCVG Survey (Point detection and sizing of insulation

BIL BOTAS INTERNATIONAL DCVG SURVEY

As Enermak Enerji, the 252 km DCVG survey project of BOTAŞ International Limited has been undertaken and completed successfully by our specialists. BOTAŞ International Limited, which their first

Konya Ilgın Çavuşçugöl site CIP Survey Service Completed.

Our CIP-Survey application on the displacement of 28.000 meters of Ilgın Çavuşçugöl Natural Gas Pipeline in Konya was successfully completed.[gallery:21]